


Birimşe Stream, Sincik, Adıyaman01.04.2009
The Sırımtaş HPP project is located on the Birimşe Stream within the borders of the Sincik District in Adıyaman Province. The foundation of the project was laid with the production license obtained on April 1, 2009. Following the acquisition of the necessary permits, construction activities commenced in May 2010. The project involves the construction of a reservoir area with a volume of 33,863,512 m³, a 4,557-meter transmission channel, a loading pool, a 719-meter pressure pipe, and the power plant building. The completion of the facility was finalized in December 2013, and it was commissioned for operation.
